When a generator changeover panel throws a fault during a DEWA outage or a routine test, you need to know how to reset Socomec CTI63 equipment quickly and safely. One wrong move can leave a building without backup power, so the order in which you do your checks matters.
On the CTI63, a software fault is normally cleared by opening and closing the Auto/Manu front cover again, then checking that the Fault LED goes out. This guide explains the full CTI63 reset procedure, how to read the LEDs, why faults happen in UAE heat, and when to call a qualified ATS engineer in Dubai, Abu Dhabi, or Sharjah.
What Is the Socomec CTI63 Transfer Panel?
The CTI63 is a 63 A wall-mounted automatic transfer panel from the CTI range, which FG Wilson lists from 63 to 160 A. It sits between the utility supply and a standby generator and moves the load from one source to the other. The range documentation carries Socomec references, and the panel has a built-in 4-pole motorised changeover switch with electronic control, built to IEC 60947-6-1.
The CTI63 is made for sites with a modest current demand, like small commercial units and compact plant rooms. Still, a failed changeover on a small site can stop tills, pumps, lifts, or access control, so the panel needs proper care.
What the panel does
- Monitors the voltage and frequency of the mains and the generator.
- Sends a start/stop signal to the generator.
- Transfers the load automatically or by hand.
- Runs tests both off load and on load.
- Shows status on LEDs and an LCD display.
Auto and manual mode
The front cover is the key to any CTI63 reset. When the cover is closed, the panel is in automatic mode. When the cover is open, it is in manual mode and the handle can be inserted. A padlock can only be fitted in manual mode, and while it is fitted, the panel can’t operate electrically or go back to auto.
Keep the manual close
Store the CTI operators instruction manual (PDF) with the panel. It is the manufacturer’s reference for LEDs and fault finding. This article adds to it and doesn’t replace it.
Before You Reset: Safety Checks for UAE Sites
Safety note: According to the manual, installation and commissioning must be done by competent, qualified personnel, and maintenance must be done by authorised, trained personnel. In the UAE, follow your site permit-to-work and the rules of the utility that serves the building, whether it’s DEWA, ADDC, or SEWA. If you are not qualified, stop here and call a specialist.
Run the quick checks first
The manufacturer’s fault-finding guide starts with simple items. Many reported “faults” go away once you confirm that:
- The switch is not padlocked.
- The manual handle has been taken out of its housing.
- The mains and generator breakers are ON (position 1).
- The generator control panel is set to Auto. If it is not, our team can help through generator services.
- No timer is still counting down on the display.
Know what opening the cover does
The panel goes into manual mode when the front cover is opened. While it is open, no automatic transfer takes place. If the mains fail at that moment, the load won’t move to the generator on its own. So, warn the site team, keep the cover open for as short a time as possible, and stay at the panel.
How to Reset Socomec CTI63 Step by Step
The steps below follow the operators and technical manuals. The same action clears software faults and a test on load that needs to be reset.
- Record the condition. Write down which LEDs are lit (Fault synthesis, Power supply, AUT) and any message on the display. A photo on your phone helps the service engineer later.
- Clear the simple causes. Remove the padlock, take out the handle, and check the breakers and generator mode, as listed above.
- Warn the site. Make sure the building can run without automatic transfer for a short time.
- Open the Auto/Manu front cover. The panel switches to manual mode.
- Close the cover again. The manual shows the cover closing with a click, which puts the panel back into automatic mode.
- Check the LEDs. The Fault synthesis LED should be off and the AUT LED should be on. The fault-finding guide also treats a blinking Power supply LED as normal.
- Stop if the fault returns. Do not repeat the action over and over. Write down what you see and call a service engineer.
Resetting a test on load
To reset a test on load, the technical manual says to open the front cover. Use the same open-and-close action, and then check that the load is back on the source you expect. If the panel stays on the generator, see the retransfer inhibit and timer notes in the next section.
Power-cycling as a last resort
If the Fault LED won’t clear, a qualified person may need to power the panel down. The technical manual says to leave the unit without power for at least three minutes so it can discharge before power-up, after which the software version shows up on the display. Power-cycling usually interrupts the load, so plan it carefully and follow your site isolation procedure.
What not to do
- Do not change keypad parameters to “fix” a fault. The keypad is password protected, and a wrong setting can stop transfer altogether.
- Do not force the handle. The manual tells you to check the direction of rotation and the torque applied.
- Do not guess passwords or settings. If a detail isn’t clear, check the official manual.
Reading the CTI63 LEDs and Common Symptoms
LEDs give the fastest diagnosis. The table below summarises the symptoms in the manufacturer’s fault-finding guide and the first checks it recommends.
| Symptom | What to check first |
| AUTO LED is off | Padlock fitted? Handle removed? Close the Auto/Manu cover. |
| Fault synthesis LED is on | Reset by opening and closing the cover. If it comes back, call a service engineer. |
| Power supply LED not blinking | The guide says to talk to your local dealer or service provider. |
| Mains LED is off | Run the lamp test, check the 1RT timer, and confirm that the mains breaker is ON. |
| Genset LED is off after start | Run the lamp test, check the 2AT timer, and make sure the generator breaker is ON. |
| No transfer to generator on mains failure | Check the 1FT timer and make sure that the generator control is set to Auto. |
| No transfer back to mains | Look for a blinking RTI LED and press the RTI button; make sure the mains LED is on. |
| Generator keeps running after mains return | The 2CT run-on timer may still be counting down. Wait until it finishes. |
Timers that look like faults
A lot of “failure to transfer” calls are just a timer that is still running. The operators manual lists these timers:
- 1FT: loss-of-mains validation, 3 seconds.
- 2AT: generator stabilisation, 5 seconds.
- 1RT: mains return validation, 180 seconds.
- 2CT: generator run-on (cool-down), 180 seconds.
- 0DT: dead band before changing source, 3 seconds.
Switch error
The technical manual describes a red error LED for a switch error: an auxiliary contact did not confirm a command from the software. Opening and closing the cover clears a one-off event. If it happens again, it points to a mechanical or auxiliary-contact problem that needs an engineer.
Why CTI63 Faults Appear in Dubai Heat and Dust
The grid in Dubai is very reliable. DEWA recorded just 0.82 minutes of customer minutes lost per customer in 2025, against roughly 15 minutes for leading European Union utilities. This is great news for the city, but it means a transfer panel may sit unused for months. A hidden fault then only shows up during a test or a real outage, which is the worst time to find it.
Heat and derating
The conditions-of-use page in the operators manual gives -10 to +40 °C without de-rating and +40 to +65 °C with de-rating. In our commissioning and maintenance work across UAE sites, enclosures in sun-exposed or badly ventilated plant rooms are the first places we check when a controller behaves erratically. Always look over the manual’s de-rating guidance for hot locations.
Dust and humidity
The enclosed panel is rated IP41, and the manual also allows 80% humidity without condensation at 55 °C. Over time, fine desert dust, coastal humidity, and gaps where cables enter can still affect terminals and contacts. Keep doors and glands sealed, and have a qualified engineer inspect the terminations during routine maintenance.
Preventive habits that reduce faults
- Run a scheduled test on load so that the changeover is exercised regularly.
- Check that the generator starts and stabilises within the panel’s timers.
- Review generator and panel capacity with a load analysis study when site demand has grown.
- Treat the panel as part of your wider critical power solutions, not as a stand-alone box.
Socomec CTI63 Reset: DIY or Professional Service?
For a trained operator, a cover reset is a reasonable first step. Anything beyond it should go to a qualified specialist. The comparison below shows where the line usually falls.
| Situation | Operator-level action | Qualified engineer |
| One-off Fault LED, clears after cover reset | Reset, log the event, monitor | Optional review at next service |
| Fault returns after reset | Stop resetting | Diagnose switch, auxiliary contacts and control |
| Load does not transfer during an outage | Switch to manual only under site procedure | Investigate the cause and restore auto operation |
| Parameter or timer changes needed | Do not change | Review and set against site requirements |
| Heat marks, odour or damaged terminals | Isolate per procedure | Inspect and repair |
| Generator and panel not coordinating | Record symptoms | Review with generator and protection settings |
If the CTI63 is part of a larger changeover scheme, the fault may not be in the panel at all. Protection settings, cable sizing, and generator behaviour can all trigger repeat events. A power system protection study helps confirm that the protection chain works as one system. For routine testing, diagnostics and repairs, our STS and ATS services cover transfer equipment across the UAE.
Get CTI63 Support in Dubai, Abu Dhabi and Sharjah
To reset a Socomec CTI63 correctly, check the simple causes, open and close the Auto/Manu cover again, check the LEDs, and stop if the fault comes back. Follow the safety notes, keep the manual with the panel, and never change settings that you can’t verify.
DCPS Middle East supports, services, and integrates power systems, including transfer panels, UPS, and generators, for facilities all over the UAE. Contact our team with the panel nameplate, a photo of the LEDs and a short description of the fault, and we will advise on the next step.